1. Check for underground sprinkler water lines and electrical lines before you dig.
  2. Dig a 22’’ hole with a tapered diameter
  3. Put 2’’ of gravel under base of sleeve, (allows for drainage) tamp stone.
  4. Place aluminum sleeve (bead down) with bottom section of flagpole into place so cement won’t fill bottom of sleeve.
  5. Mix bag of cement (40 pound bag) and pour into hole.
  6. Mound up concrete around sleeve to allow for water runoff.
    (Add rocky fill to increase concrete volume).
  7. Use level to square vertical. Stabilize for 24 hours. Insert remaining sections.